Construction Update

August 2026 Construction Progress at 10-32 47th Ave

Long Island City, New York

A monthly report for EB-5 investors in the 10-32 47th Ave project, covering August 1 through August 31, 2026. The building topped off this month, and HVAC ductwork, plumbing rough-in and wall framing are all moving forward.

Concrete pump and mixer trucks working in front of the 10-32 47th Ave building
The project site in August. Source: August 2026 construction report.

August at a Glance

Structure
Topped off
HVAC
Ductwork rough-in under way
Plumbing
Pipe rough-in under way
Wall Systems
Exterior and interior framing under way

Source: Amara Holding Group & BARC.

The Structure Has Topped Off

The project topped off in August. Topping off means the building’s structure has reached its highest designed elevation and the structural work that goes with it is complete.

Street view of the topped-off concrete structure wrapped in scaffolding
The topped-off structure. Source: August 2026 construction report.

HVAC and Plumbing Rough-In Under Way

HVAC ductwork rough-in is in progress. This is the stage where the ducts that will heat, ventilate and cool the building are positioned and installed, along with the connection points that later equipment ties into.

Plumbing rough-in is moving in parallel. Supply and drain lines and their fittings are being run and set now, work that is typically finished before the walls and ceilings are closed up.

Overhead drain lines and ductwork installed beneath the concrete slab
HVAC and plumbing rough-in in progress. Source: August 2026 construction report.

Wall Framing in Progress

Framing of the exterior and interior walls is in progress. The framing is the skeleton of each wall. It establishes the exterior wall build-up and the layout of the interior spaces, and it is what the wall enclosure and the installation work that follows attach to.

Steel wall studs staged on a floor still fitted with shoring posts
Wall framing under way inside the building. Source: August 2026 construction report.
A worker beside staged concrete blocks and formwork panels during interior framing
Block and framing materials staged for the interior walls. Source: August 2026 construction report.

Where the Project Stands as of August 31

As of August 31, the structure has topped off, and HVAC ductwork rough-in, plumbing rough-in and wall framing are all progressing. We will keep updating investors on construction in the monthly reports that follow.

This update is prepared for EB-5 investor clients in the project and covers the reporting period from August 1 to August 31, 2026.

BARCEB-5 investment and immigration planning, from New York since 2013.

Begin the Conversation

Planning for Your Family’s Future Starts Today

Connect with our team to explore EB-5 opportunities and discuss your long-term goals.

Request a Callback