A monthly report for EB-5 investors in the 10-32 47th Ave project, covering August 1 through August 31, 2026. The building topped off this month, and HVAC ductwork, plumbing rough-in and wall framing are all moving forward.

August at a Glance
- Structure
- Topped off
- HVAC
- Ductwork rough-in under way
- Plumbing
- Pipe rough-in under way
- Wall Systems
- Exterior and interior framing under way
Source: Amara Holding Group & BARC.
The Structure Has Topped Off
The project topped off in August. Topping off means the building’s structure has reached its highest designed elevation and the structural work that goes with it is complete.

HVAC and Plumbing Rough-In Under Way
HVAC ductwork rough-in is in progress. This is the stage where the ducts that will heat, ventilate and cool the building are positioned and installed, along with the connection points that later equipment ties into.
Plumbing rough-in is moving in parallel. Supply and drain lines and their fittings are being run and set now, work that is typically finished before the walls and ceilings are closed up.

Wall Framing in Progress
Framing of the exterior and interior walls is in progress. The framing is the skeleton of each wall. It establishes the exterior wall build-up and the layout of the interior spaces, and it is what the wall enclosure and the installation work that follows attach to.


Where the Project Stands as of August 31
As of August 31, the structure has topped off, and HVAC ductwork rough-in, plumbing rough-in and wall framing are all progressing. We will keep updating investors on construction in the monthly reports that follow.
This update is prepared for EB-5 investor clients in the project and covers the reporting period from August 1 to August 31, 2026.